【单选题】【消耗次数:1】
A hunter is a man who ___ animals.
catch
catches
will catch
was catching
参考答案:
复制
纠错
相关题目
【单选题】 A hunter is a man who __________ animals.
①  catch
②  catches
③  will catch
④  was catching
【单选题】 A hunter is a man who______ animals.
①  catch
②  catches
③  will catch
④  was catching
【单选题】 3.A hunter is a man who animals.
①  catch
②  catches
③  will catch
④  was catching
【单选题】 By cutting down trees we ____ the natural home of birds and animals.
①  harm
②  hurt
③  injure
④  damage
【单选题】 _____ that we couldn’ t catch up with him.
①  So fast he ran
②  So fast did he run
③  So fast ran he
④  Such fast did he run
【单选题】 Peter could hardly catch what I said, _____ he?
①  could
②  couldn’ t
③  did
④  didn’ t
【单选题】 What animal do you like [填空]? I like all kinds of animals.
①  better
②  best
③  very
④  well
【判断题】 3.try-catch语句不可以嵌套使用。( )
①  正确
②  错误
【单选题】 如果?个程序段中有多个catch,则程序会按下列哪种情况执?( )。
①  对每个catch都执??次
②  找到合适的异常类型后就不再执?后边的catch
③  找到每个符合条件的catch都执??次
④  找到合适的异常类型后继续执?后?的catch
【单选题】 12. We didn’t catch the train _______ we left late.
①  so
②  because
③  but
④  though
随机题目
【单选题】 C三个施工过程组成,有2个施工层;现划分为四个施工段,流水节拍均为3d,试组织流水施工,该项目工期为()。
①  21
②  48
③  30
④  20
【单选题】 双代号网络中只有内向箭线无外向箭线段的结点是()。
①  起始结点
②  结束结点
③  中间结点
④  任意结点
【单选题】 起点流向以及()。
①  材料的堆放布置
②  现场准备工作
③  施工方法及施工机械
④  技术和组织措施
【单选题】 在进行网络计划费用优化时,应首先将()作为压缩持续时间的对象。
①  直接费用率最低的关键工作
②  直接费用率最低的非关键工作
③  直接费用率最高的非关键工作
④  直接费用率最高的关键工作
【单选题】 单代号网络计算总时差的过程是:()
①  自开始结点顺箭杆方向至结束结点
②  自结束结点逆箭杆方向至开始结点
③  工作时间→节点时间→计算总时差
④  节点时间→工作时间→计算总时差
【单选题】 单代号网络中出现若干同时结束工作时,采取的措施是:()
①  虚设一个虚工作
②  虚设一个结束节点
③  构造两个虚设节点
④  增加虚工序表示结束节点
【单选题】 自由时差,是各项工作在不影响紧后工作()
①  最早开始
②  最早结束
③  最迟开始
④  最迟结束
【单选题】 下列哪一个不是评价单位工程施工进度计划质量的指标。()
①  主要施工机械的利用程度
②  劳动生产率
③  资源消耗的均衡性
④  工期
【单选题】 若工作的延误时间大于该工作的自由时差,小于总时差,说明此延误时间对后续工作有影响,对总工期()。
①  有影响,但可不作调整
②  有影响,必须调整
③  无影响,且不需调整
④  虽无影响,但要调整
【单选题】 香蕉图的绘制依据是工作的()。
①  最早开始时间和最迟开始时间
②  最早开始时间和最迟结束时间
③  最迟开始时间和最迟结束时间
④  最迟开始时间和最早开始时间